CF1R, CF2R and CF3R Forms Explained in Plain English

A residential Title 24 project may involve several forms with similar names: CF1R, CF2R and CF3R. Although they belong to the same compliance process, each form records a different stage of the project.

The simplest way to understand them is this: the CF1R describes the approved design, the CF2R confirms how the work was installed, and the CF3R records required field verification or diagnostic testing.

architectural drawing images title 24

The Three Forms at a Glance

These documents work together to connect the approved energy design with the completed construction. The California Energy Commission identifies CF1R, CF2R and CF3R as the Certificate of Compliance, Certificate of Installation and Certificate of Verification, respectively.

Energy Code Forms Table
FORM FULL NAME MAIN PURPOSE PROJECT STAGE
CF1R Certificate of Compliance Shows that the proposed design meets the Energy Code Design and permit stage
CF2R Certificate of Installation Confirms that energy-related components were installed as required Construction stage
CF3R Certificate of Verification Documents required field verification or diagnostic testing Inspection and verification stage

What Is a CF1R?

The CF1R is the document most homeowners encounter first. It is prepared during the design and permit phase and explains how the proposed project will meet California’s residential energy-efficiency requirements.

The information may be entered directly into a prescriptive form or generated using approved compliance software such as CBECC-Res. The completed CF1R is normally coordinated with the construction drawings and submitted to the local building department.

You can send us your plans and a short description of the work. We will review the documents and let you know whether anything else is needed.

CF1R Information Table
CF1R INFORMATION WHAT IT DESCRIBES COMMON SOURCE WHY IT MATTERS
BUILDING GEOMETRY Floor area, orientation and envelope dimensions Architectural plans Establishes the energy model
ENVELOPE FEATURES Insulation, windows, doors and roofing Plans and schedules Determines thermal performance
MECHANICAL SYSTEMS HVAC equipment, ducts and ventilation Mechanical plans Defines system efficiency
WATER HEATING Water-heater type and performance Plumbing plans Affects projected energy use

The CF1R demonstrates that the project design and specified equipment comply with the Energy Code at the time of permit application.

california energy commission residential forms

What Is a CF2R?

The CF2R is completed during construction. It is used to confirm that regulated building components and systems were installed according to the approved plans, the CF1R and the applicable Energy Code requirements.

There is not necessarily one CF2R for the entire project. Different installers may complete separate forms for insulation, windows, HVAC equipment, duct systems, ventilation or water heating.

Installation Areas Table
INSTALLATION AREA TYPICAL RESPONSIBLE PARTY WHAT IS CONFIRMED EXAMPLE
INSULATION Insulation contractor Type, location and installed value Wall or attic insulation
HVAC SYSTEM Mechanical contractor Equipment and installation details Heat pump or air conditioner
DUCTWORK HVAC contractor Duct location, insulation and sealing Attic duct system
WATER HEATING Plumbing contractor Equipment and installation details Heat-pump water heater

A CF2R should reflect what was actually installed. Substituting equipment or changing an assembly during construction may require the energy documents to be reviewed and possibly revised.

Note: This form falls outside the current scope of services offered by Title24Deal.comA CF2R should reflect what was actually installed. Substituting equipment or changing an assembly during construction may require the energy documents to be reviewed and possibly revised.

What Is a CF3R?

The CF3R is used when the project includes measures that require independent field verification or diagnostic testing. Under the 2025 Energy Code, these activities are referred to as Energy Code Compliance verification, although many industry professionals may still use the familiar term “HERS testing.”

The CF3R must be completed by a certified Energy Code Compliance rater for the applicable measure.

Verification Measures Table
VERIFICATION MEASURE WHAT THE RATER CHECKS TYPICAL METHOD COMMON RESULT
DUCT LEAKAGE Air escaping from the duct system Pressure testing Pass or corrective work
REFRIGERANT CHARGE Proper air-conditioning operation Diagnostic measurements Verified equipment performance
AIRFLOW Air delivered through the system Field measurement Confirmed airflow rate
INSULATION QUALITY Installation quality and coverage Visual field inspection Verified insulation installation

Not every project requires a CF3R. The CF1R normally identifies whether verification measures are included. When verification is required, the related compliance documents must be completed and registered through an approved provider registry.

Who Prepares Each Form?

Form Responsibilities Table
FORM USUALLY PREPARED BY SIGNED OR CERTIFIED BY MAIN RECIPIENT
CF1R Energy consultant or documentation author (Title24Deal.com) Documentation author and responsible project party (Title24Deal.com) Building department
CF2R Installing contractor or responsible installer Person responsible for the installation Inspector or registry
CF3R Certified ECC rater Certified field-verification professional Inspector and registry
FINAL DOCUMENT SET Builder or project coordinator Applicable responsible parties Building owner

The project team should retain the completed compliance documents. The 2025 Residential Compliance Manual indicates that applicable CF1R, CF2R and CF3R documentation should be included with the homeowner’s manual, so the owner has a record of the installed energy features.

Why These Forms Matter

The three forms create a practical chain of responsibility. The CF1R establishes what the project is designed to include. The CF2R confirms that the specified components were installed. The CF3R verifies selected measures that require independent testing or inspection.

Keeping these documents coordinated helps prevent permit corrections, failed inspections and disagreements about what the approved design required.